Meta Agrees to Fund Local Energy Infrastructure for Louisiana Data Center

By Nicholas G. Miller


Meta agreed to a deal with Entergy Louisiana through which it will pay for new energy infrastructure to support its data center in Northeast Louisiana.

Meta will fund seven new natural gas power plants totaling more than 5,200 megawatts, 240 miles of 500 kilovolt transmission lines, and battery energy storage across three locations.

Meta also committed to help fund up to 2,500 megawatts of new renewable resources and agreed to a memorandum of understanding to explore the future development of nuclear power.

Entergy said the deal would ensure Meta pays its full cost of service and would deliver about $2 billion in customer savings over 20 years.


Write to Nicholas G. Miller at nicholas.miller@wsj.com


(END) Dow Jones Newswires

March 27, 2026 09:42 ET (13:42 GMT)

Copyright (c) 2026 Dow Jones & Company, Inc.

The articles, information, and content displayed on this webpage may include materials prepared and provided by third parties. Such third-party content is offered for informational purposes only and is not endorsed, reviewed, or verified by Morningstar.

Morningstar makes no representations or warranties regarding the accuracy, completeness, timeliness, or reliability of any third-party content displayed on this site. The views and opinions expressed in third-party content are those of the respective authors and do not necessarily reflect the views of Morningstar, its affiliates, or employees.

Morningstar is not responsible for any errors, omissions, or delays in this content, nor for any actions taken in reliance thereon. Users are advised to exercise their own judgment and seek independent financial advice before making any decisions based on such content. The third-party providers of this content are not affiliated with Morningstar, and their inclusion on this site does not imply any form of partnership, agency, or endorsement.

Popular

Sponsor Center